TBM OLGA REACHES ITS DESTINATION: Nine tunnel boring machines shaped the mechanised excavation of the Brenner Base Tunnel

With the breakthrough of the tunnel boring machine Olga, the mechanised excavation phase of the Brenner Base Tunnel has been completed.

 

On 24 November, the tunnel boring machine (TBM) Olga reached its destination. Its breakthrough marks the completion of all mechanised excavation works for the Brenner Base Tunnel. Olga was deployed on the H53 Pfons–Brenner construction lot, excavating the eastern main tunnel tube towards Innsbruck.

This milestone is an opportunity to look back at the remarkable technical achievements of the tunnel boring machines that have played a defining role in the construction of the Brenner Base Tunnel over many years. In total, nine TBMs were used on the project. Eight of these machines were manufactured by the German company Herrenknecht. Each machine was specifically designed for different construction sections and requirements and adapted to the geological and engineering conditions it encountered.

 

Wolfgang Holzer, Director of Construction Innsbruck–Brenner, BBT
“The breakthrough of Olga stands as a symbol of the tremendous technical and organisational achievement behind the Brenner Base Tunnel construction sites. Mechanised tunnelling requires the precise coordination of numerous trades, highly specialised technology and experienced teams.
This success is the result of the dedicated work of many people over a long period of time.”

Michael Knapp, Project Manager H53 Pfons–Brenner
“For our construction lot, Olga’s breakthrough marks the conclusion of an intensive excavation phase.Over the course of its journey, the machine excavated approximately 7.6 kilometres through the mountain. Throughout the process, excavation operations had to be continuously adapted to geological conditions, while machine operations were carefully coordinated with all associated works. I would like to thank all employees and the companies involved for their commitment, professionalism and outstanding work.”

 

Olga: High-Performance Engineering in Action
Olga is approximately 183 metres long and weighs around 2,600 tonnes. Its cutterhead has a diameter of 10.37 metres. The machine is equipped with an installed drive power of 4,550 kilowatts and generates a torque of 26,400 kilonewton metres.
Since beginning excavation on 18 September 2024 in the H53 Pfons–Brenner section, Olga has driven approximately 7.6 kilometres of tunnel. The rotating cutterhead excavated the rock, while conveyor systems transported the excavated material away from the face. At the same time, precast concrete segments, known as segmental lining rings, were installed to form the permanent lining of the mechanically excavated tunnel section.

Nine Machines, Different Technical Challenges
The use of tunnel boring machines is a key method in the construction of long underground infrastructure projects. Each machine must be tailored to the geological conditions and technical requirements of the particular section it is assigned to. Factors such as rock characteristics, required excavation performance, cutterhead design and onboard equipment all influence the machine’s configuration.
A total of nine tunnel boring machines were deployed during the construction of the Brenner Base Tunnel. Their different roles and technical characteristics demonstrate the wide range of challenges involved in mechanised tunnelling through the Alps.

The Technology and People Behind the Excavation
Behind every tunnel boring machine lies a complex interaction of engineering, planning, operational control and construction site management. Machines must not only be designed and assembled, but also continuously monitored, maintained and adapted throughout the excavation process.
Olga provides a particularly striking example of this complexity. Its cutterhead, drive systems, conveyor technology and the hundreds of metres of backup equipment trailing behind the machine form a highly sophisticated technical system.
The breakthrough of Olga therefore also represents the dedication and expertise of the many specialists working on and behind the construction sites.

Mechanised Excavation Completed
With Olga’s breakthrough, all mechanised excavation works for the Brenner Base Tunnel have come to an end.
The completion of mechanised tunnelling marks both a major engineering achievement and the transition to the next phases in the construction of the Brenner Base Tunnel.