With its arrival at the Brenner Pass on 2 May 2025, Flavia completed the mechanical excavation of the BBT on the Italian side of the project.
After covering more than 14 kilometres, the double-shield TBM had reached the national border. Following Serena and Virginia, Flavia was the third tunnel boring machine to complete the journey from Mules to the Brenner Pass.
This special event was celebrated on 15 May 2025 in the presence of representatives of the Italian, Austrian and European authorities, as well as the miners and the BBT SE team.
Old Crystalline formations: This strongly foliated, fine-grained rock consists predominantly of quartz, mica and feldspar. It formed from fine-grained marine sediments of Palaeozoic age, which were transformed into mica schist and paragneiss during the formation of the Alps.
The Palaeozoic (also known as the Paleozoic Era or the “Age of Ancient Life”) spans the geological period from approximately 538.8 to around 251.9 million years ago.
Mountain building, or orogeny, refers to the formation of mountain ranges through the deformation of rock masses over geological timescales.
Bündner schists: This strongly foliated, medium- to fine-grained rock consists predominantly of carbonate, quartz and mica. It formed from marine sediments of the Mesozoic Era and was transformed into calcareous schist and, to a lesser extent, calcareous marble during the formation of the Alps. The Mesozoic Era (also known as the “Reptilian Age”) is a geological era that began approximately 252 million years ago and ended around 66 million years ago.
Central gneiss: This slightly foliated rock consists mainly of quartz, feldspar and mica. It formed from intrusive igneous rock (granite or granodiorite) and was transformed mainly into orthogneiss during the formation of the Alps. In geology, “intrusive” refers to rocks or geological structures formed by the intrusion of magma into pre-existing rock.
After overcoming some of the hardest and most abrasive rock formations in the entire Alpine region, TBM Flavia was dismantled directly on the construction site.
In geology, the term “abrasive” refers to a material or process that has a grinding, rubbing or wearing effect on rocks and minerals.
In April 2023, TBM Flavia stopped approximately 3.5 kilometres from the Brenner. The high overburden of more than 1,200 metres and the unstable, heavily fractured rock caused the rock mass to exert pressure on the TBM, blocking excavation progress for several months. After several restart attempts, Flavia was finally able to resume operation and continued tunnelling. In May 2025, following this technically demanding stage, it reached its destination at the Brenner.
Geological fault zone
A fault zone is a tectonically formed fracture zone in the rock mass where sections of rock have shifted relative to one another. As it made its way through the mountain, this tunnel boring machine encountered a wide variety of rock types at short intervals, including schist, phyllite, quartzite, marble and rauhwacke.
These rock sequences are intersected by fault zones. Over time, tectonic movements of the continental plates caused the rock in this area to become heavily fractured and crushed.
A double challenge
For Flavia, the challenge was not only to drive the west main tunnel through extremely difficult fault zones. During excavation, more than 65,000 tunnel segments were installed simultaneously to form the tunnel’s inner lining. The tubbing segments were manufactured at the Hinterrigger plant near the Mules construction site, which operated from 2017 to 2024 to produce the BBT tunnel lining segments. From there, the precast concrete elements were transported by rail directly to TBM Flavia.