Clio, Günther, Serena, Virginia, Flavia, Ida, Lilia, Olga, Wilma

GIANTS IN THE MOUNTAIN

9 TUNNEL BORING MACHINES – 1 COMMON GOAL:
to successfully complete the mechanical excavation of the Brenner Base Tunnel whilst, for the most part, installing the tunnel lining at the same time.

Approximately half of the Brenner Base Tunnel system will be excavated mechanically, with tunnel boring machines (TBMs).

The choice of tunnelling method depends on various economic and logistical factors, such as the length of the section to be excavated, the type of rock being excavated, the financial resources available and the construction times.
 

In operation in the Brenner Base Tunnel

DIFFERENT TYPES OF TUNNEL BORING MACHINES

TBM GÜNTHER, CONSTRUCTION LOT H33 TULFES-PFONS

‘OPEN’ GRIPPER TUNNEL BORING MACHINE

This TBM has a relatively short shield behind the cutting head. This provides a direct view of the rock face. The ‘open’ TBM is used solely for tunnelling work.

The tunnel is being stabilised behind the TBM: Tunnel workers install steel mesh and rock bolts, besides other consolidation elements, and apply shotcrete to the tunnel wall.

TBMS IDA AND LILIA, CONSTRUCTION LOT H41 SILL GORGE-PFONS

‘CLOSED’ SINGLE-SHIELD TBMS

This type of TBM has a single shield skin.  Whilst drilling takes place at the front, the tunnel is stabilised directly behind the cutterhead using tubbing rings, i.e. prefabricated concrete segments Tunnel excavation usually stops briefly whilst the tunnel segments are being installed.

TBMS WILMA AND OLGA, CONSTRUCTION LOT H53 SILL GORGE-PFONS TBMS SERENA, VIRGINIA AND FLAVIA, CONSTRUCTION LOT H61 MULES TBM CLIO, CONSTRUCTION LOT E91

‘CLOSED’ DOUBLE-SHIELD TBMS

This TBM has a front and a rear shield. The machine can push itself forward off the rock, using so-called grippers. This allows tunnel excavation and tubbing ring installation to take place simultaneously. 

THE 9 TUNNEL BORING MACHINES OF THE BBT