THE BRENNER PASS:

THE MOST IMPORTANT ALPINE CROSSING


In the early Bronze Age, around 1,700 CE, this mountain pass was an important commercial link between the North Sea and the Mediterranean countries.

 

 

In the 14th century, 3,000 tons of freight including spices, wine, sugar, oil and cotton were transported over the Brenner Pass every year. The flow of goods over the Brenner increased constantly, so that by the beginning of the 19th century the volume of goods being carried over the Brenner every year, using horse-drawn wagons, had risen to 15,000 tons and then to 60,000 tons only 50 years later. This soon led to capacity bottlenecks and the construction of the Brenner Railway.

The current route  was built between 1860 and 1867. A hundred years later, the motorway was built. Since 1974, the Brenner Pass can be crossed on the Austrian A13 and the Italian A22 motorways. After completion of the motorway, ten million tonnes of goods were transported across the Brenner Pass each year; today, around 40 million net tonnes are transported by road.

PROJECT MILESTONES

20.08.2007   

 

Start of construction on the Mules access tunnel (Italy): 1.8 km, gradient 9.3%, cross-section 92 m², excavated by blasting

 

28.04.2008

 

Start maschineller Vortrieb Erkundungsstollen Aicha (Italien): 10,5 km, Doppelschildmaschine (6,3 m Durchmesser)

 

23.10.2009

 

Completion of the Mules access tunnel (Italy)

 

04.12.2009

 

Start of mechanized excavation on the Aica exploratory tunnel (Italy): 10.5 km, double-shield tunnel boring machine (6.3 m in diameter)

 

16.07.2010

 

Start of construction in Austria: Sill Gorge exploratory tunnel: 5.4 km, cross-section 26 m², excavated by blasting

 

03.11.2010

 

Breakthrough on the exploratory tunnel in Aica (Italy)

 

04.04.2011

 

Start of construction on the Wolf I construction lot (Steinach am Brenner, Austria): Logistics tunnels: Saxener tunnel and Padaster tunnel

 

19.09.2011

 

Start of excavation on the Ampass access tunnel (Austria): 1,350 m, cross-section 35 m², gradient 10%, excavated by blasting

07.10.2011

 

Start of construction work on the Periadriatic line construction lot (Italy): 3.7 km of main tunnels, 1.5 km of exploratory tunnel, contract amount 53.1 million EUR

 

24.06.2011

 

Breakthrough on the Padaster tunnel (WOLF I construction lot, Steinach a.Br./Austria)

 

24.02.2012

 

Breakthrough on the Saxen tunnel (WOLF I construction lot, Steinach a.Br./Austria)

 

11.10.2012

 

Completion of the Ahrental access tunnel = Breakthrough on the Ahrental access tunnel to the Sill Gorge exploratory tunnel

 

01.07.2013

 

Completion of the Ampass access tunnel (Austria)

 

04.12.2013

 

Start of excavation work on the Wolf II construction lot (Austria): Access tunnel: Length 4 km, cross-section 120 m²,  gradient 10%, spoil removal tunnel 950 m, work on the Padaster valley disposal site

 

11.12.2013

 

Completion of the Sill Gorge stretch of the exploratory tunnel (Austria)

 

22.04.2014

 

Start of works on the Patsch shaft (Austria), 180 m, excavated by blasting

 

04.09.2014

 

Completion of the Patsch shaft (Austria)

 

18.09.2014

 

Start of excavation work on the Tulfes-Pfons construction lot (Austria): 380 million EUR, 38 km, Construction time 55 months

 

31.10.2014

 

Start of works on the Isarco river underpass construction lot (Italy): 301 million EUR, 4.2 km of main tunnels, 1.8 km of connecting tunnels

 

14.02.2015         

Breakthrough on the 950 m long spoil removal tunnel  (Wolf II construction lot, Austria)

 

 

19.03.2015

 

First blast on both main tunnels in Ahrental (Tulfes-Pfons construction lot, Austria) in the presence of EU-Commissioner Violeta Bulc and the Ministers of Transport of the 7 Alpine States and Regions

 

 

25.03.2015

 

Completion of the construction lot Periadriatic line ( Italy)

 

 

26.09.2015

 

Start of TBM excavation on the Ahrental-Pfons stretch of the exploratory tunnel (Austria):17 km, 200 m open gripper tunnel boring machine, 8 m in diameter

 

 

22.12.2015

 

Completion of the Wolf access tunnel

 

 

05.01.2016

 

Start of excavation work on the Wolf stretch of the exploratory tunnel

 

 

06.12.2016

 

Start of excavation work on the Mules 2-3 construction lot: 993 million EUR, 40 km of main tunnels, 15 km of exploratory tunnel, 10 km logistics and connecting tunnels, construction time 7 years

 

 

11.05.2017

 

Tulfes- Pfons construction lot: Breakthrough on the east connecting tunnel

 

 

04.07.2017

 

Tulfes- Pfons construction lot: Breakthrough on the west connecting tunnel

 

 

20.07.2017

 

Tulfes- Pfons construction lot: Breakthrough on the emergency tunnel for the Innsbruck bypass

 

 

04.12.2018

 

Breakthrough on the south portal in Fortezza

 

 

02.02.2019

 

Start of excavation work on the Pfons-Brenner construction lot: 966 million EUR, 37 km of main tunnels, 9 km of exploratory tunnel, 6 km logistics and connecting tunnels, construction time 6 years

 

 

12.02.2019

 

Tulfes- Pfons construction lot: Breakthrough on the Ahrental evacuation tunnel

 

 

29.03.2019

 

Start of excavations on the southern part of the exploratory tunnel from Wolf to Brenner

 

 

30.04.2019

 

100 km of tunnels have been excavated

 

 

22.05.2019

 

Mules 2-3 construction lot: Start-up of the last of the three TBMs excavating the Brenner Base Tunnel southwards: After Serena (5.5.2018) and Flavia (16.4.2019), Virginia sets off on its approximately 14.3 km long journey. The destination of all three TBMs is the national border at the Brenner Pass

 

 

01.07.2019

 

Start of excavations on the Pfons-Brenner construction lot

 

 

29.11.2019

 

Half of the excavation work has been completed

 

 

01.03.2020

 

Start of operations at Ahrental power station by Innsbrucker Kommunalbetriebe (IKB) and BBT SE

 

 

06.07.2020

 

Exploratory tunnel breakthrough in the Steinach am Brenner area

 

 

03.08.2020

 

Isarco underpass construction site: Start of excavations below the river

 

 

15.10.2020

 

Isarco underpass construction site: Start of excavations below the river

 

 

10.11.2020

 

Isarco underpass construction site: First breakthrough below the Isarco river

 

 

08.02.2021

 

Isarco underpass construction site: Relocation of the existing rail line completed

 

 

11.03.2021

 

Isarco underpass construction site: Start of ground freezing for the first main tube

 

 

28.10.2021

 

Start of excavation work on the future north portal Innsbruck - Sill Gorge (east main tunnel tube)

 

   

24.11.2021

 

After 3.5 years and about 14.2 km of excavation northwards by TBM Serena, the first tunnel tube in the BBT project to reach the state border at Brenner was the exploratory tunnel, 1,450 metres below the surface.

 

   

04.05.2022

 

Start of excavations on the Hochstegen construction lot

 

   

19.05.2022

 

The breakthrough between the Mules and the Isarco River Underpass construction lots provides a continuous connection between the south portal of the BBT and the State border at Brenner

 

   

07.07.2022

 

Start of excavations on the Sill Gorge-Pfons construction lot

 

   

30.03.2023

 

Construction lot H61 Mules 2-3: Arrival of TBM Virginia at the national border at Brenner Pass – after 4 years and 14.2 km of excavation of the west main tunnel northwards.

 

   

02.05.2023

 

Construction lot H41 Sill Gorge-Pfons Start of mechanised excavation with TBM Lilia (10.4 m in diameter) for 8.1 km of excavation of the east main tunnel southwards

 

   

04.05.2023

 

Construction lot H53 Pfons-Brenner: Start of excavation work on 15.2 km of main tunnel using a TBM, 10 km of main tunnel using drill and blast, 1.3 km of exploratory tunnel, 2.6 km of cross-connecting tunnels, construction to last approx. 6 years, 959 million EUR

 

   

27.06.2023

 

Construction lot H41 Sill Gorge-Pfons Start of mechanised excavation with TBM Ida (10.4 m in diameter) for 8.4 km of excavation of the west main tunnel southwards

 

   

04.12.2023

 

Construction lot H71 Isarco river underpass: Completion of the construction work

 

   

15.12.2023

 

Construction lot H52 Hochstegen: Completion of the construction work

 

   

17.09.2024

 

Construction lots H41 Sill Gorge-Pfons and H21 Sill Gorge: First breakthrough of a main tunnel in Austria (east main tunnel)

 

   

18.09.2024

 

Construction lot H53 Pfons-Brenner: Start of mechanised excavation with TBMs Wilma (west main tunnel) and Olga (east main tunnel) for approx. 7.5 km of excavation northwards, each 10.4 m in diameter

 

   

05.12.2024

 

Construction lot  H21 Sill Gorge: Completion of the construction work

 

   

30.01.2025  

 

Start of construction work on the construction site New Access Road Riol

 

   

02.05.2025

 

Construction lot H61 Mules 2-3: Arrival of the TBM Flavia at the national border at Brenner Pass – after 14.3 km of excavation of the west main tunnel northwards. This marks the completion of the TBM-excavation on the Italian side of the BBT.

 

   

20.05.2025

 

Construction lots H41 Sill Gorge-Pfons and H21 Sill Gorge: Breakthrough  in the west main tunnel

 

   

08.07.2025

 

200 km of tunnels have been excavated

 

   

22.08.2025

 

Construction lot H41 Sill Gorge-Pfons Arrival of the TBM Ida after 8.4 km of excavation of the west main tunnel southwards.

 

   

18.09.2025

 

Breakthrough of the exploratory tunnel at the State border at the Brenner Pass between the construction lots Mules and Pfons-Brenner. For the first time, there is a continuous underground connection between Italy and Austria.

 

   

06.10.2025

 

Construction lot H41 Sill Gorge-Pfons Arrival of the TBM Lilia after 8.1 km of excavation of the east main tunnel southwards.

 

   

28.07.2026

 

Breakthrough of the main tunnel tubes between the "Mules" and "Pfons-Brenner" construction lots at the state border at the Brenner Pass. For the first time, both main tunnel tubes are broken through simultaneously.

 

   

25.08.2026

 

H53 construction lot “Pfons-Brenner“
Breakthrough of the Wilma tunnel boring machine into the IRIS auxiliary drivage after excavating 7.45 km of the west main tunnel northwards. This milestone completes the continuous connection of all sections of the west main tunnel, stretching approximately 55 kilometres from the Sill Gorge near Innsbruck to Fortezza in Alto Adige.

 

OUR HISTORY IN PICTURES

Start of construction of the Mules access tunnel (Italy)
Start of mechanized excavation of the Aica exploratory tunnel (Italy)
Completion of the Mules access tunnel (Italy)
Start of construction in Austria
Start of construction on the Ahrental access tunnel (Austria)
Breakthrough on the exploratory tunnel in Aica (Italy)
Breakthrough on the Padaster tunnel (Wolf I construction lot, Steinach am Brenner /Austria)
Start of excavation on the Ampass access tunnel (Austria)
Breakthrough in the Saxen tunnel (Wolf I construction lot, Steinach am Brenner /Austria)
Completion of the Ahrental access tunnel = Breakthrough in the Ahrental access tunnel to the Sill Gorge exploratory tunnel
Start of excavation work on the Wolf II construction lot (Austria)
Completion of the Patsch shaft (Austria)
Start of works on the Isarco river underpass construction lot (Italy)
Start of excavation work on the Tulfes-Pfons construction lot (Austria)
Breakthrough in the 950 m spoil removal tunnel (Wolf II construction lot, Austria)
Start of TBM excavation of the Ahrental-Pfons stretch of the exploratory tunnel (Austria)
Start of excavation work on the Mules 2-3 construction lot
Tulfes- Pfons construction lot: Breakthrough east connecting tunnel
Breakthrough south portal in Fortezza
Start of excavation work on the Pfons-Brenner construction lot
Tulfes- Pfons construction lot: Breakthrough in the Ahrental evacuation tunnel
Start of excavations on the southern part of the exploratory tunnel from Wolf to Brenner
Mules 2-3 construction lot: Start-up of the last of the three TBMs excavating the Brenner Base Tunnel towards Brenner
Exploratory tunnel breakthrough in the Steinach am Brenner area
Isarco underpass construction site: Start of excavations below the river
Isarco underpass construction site: First breakthrough below the Isarco river
Isarco underpass construction site: Relocation of the existing rail line completed
Isarco underpass construction site: Start of ground freezing for the first main tube
Start of the excavation works at the future northern portal: Innsbruck - Sill Gorge (east main tunnel tube)
Start of excavations on the Sill Gorge-Pfons construction lot
Start of excavations on the Hochstegen construction lot
With the breakthrough between the Mules and the Isarco River Underpass construction lots, we now have a continuous connection between the southern portal of the BBT and the State border at Brenner Passr
Construction lot H61 Mules 2-3: Arrival of the TBM Virginia at the national border at Brenner Pass
Construction lot H41 Sill Gorge-Pfons Start of mechanised excavation with TBM Lilia
Construction lot H41 Sill Gorge-Pfons Start of mechanised excavation with TBM Ida
Construction lot H71 Isarco river underpass: Completion of the construction work
Construction lot H52 Hochstegen: Completion of the construction work
Construction lots H41 Sill Gorge-Pfons and H21 Sill Gorge: First breakthrough of a main tunnel in Austria (east main tunnel)
Construction lot H41 Sill Gorge-Pfons Arrival of the TBM Lilia after 8.1 km of excavation of the east main tunnel southwards.
BRENNER BASE TUNNEL - A PROJECT UNITING EUROPE   BRENNER BASE TUNNEL   A PROJECT UNITING EUROPE - BRENNER BASE TUNNEL