THE TBM IN FIGURES

METRES
10.37

Cutter head diametre

METRES
180

TBM total length

kW
4550

Driving power (6.188 PS)

TONS
2700

TBM total weight

TUBBING RINGS
27545

installed by TBM Olga to form the inner lining
 

24.11.2026

BREAKTHROUGH IN THE EAST MAIN TUNNEL

And at 11:00 o’clock, it was done: Approaching from the south, TBM Wilma has been working its way northwards through the final rock formations.

The breakthrough took place at the IRIS auxiliary drivage in the municipality of Navis.

This not only established the connection between the Sill Gorge–Pfons and Pfons–Brenner construction lots but also completed the continuous connection of all sections of the west main tunnel into one tunnel tube, spanning approximately 55 kilometres from the Sill Gorge near Innsbruck to Fortezza in Alto Adige.
 

The predominant rock formations along the Olga TBM drive

GEOLOGY

Bündner schists: Heavily schistose, these rocks are mainly made up of quartz, mica and calcite. The source material was deposited on the ocean floor during the Mesozoic era. During the formation of the Alps, these rocks were transformed into schist. The Mesozoic Era (also known as the “Reptilian Age”) is a geological era that began approximately 252 million years ago and ended around 66 million years ago. Mountain building, or orogeny, refers to the formation of mountain ranges through the deformation of rock masses over geological timescales.

DISMANTLING

The auxiliary drive in the “IRIS” fault zone served two important purposes: It served both as the breakthrough point at the end of the excavation drives of TBMs Wilma, Olga, Ida and Lilia, and as a disassembly chamber where the four machines were disassembled and prepared for removal from the site.

DISTINCTIVE FEATURES OF TBM OLGA

Unlike most other fault zones that Wilma and Olga had encountered, “Jana” was a flat-lying fault.

Most of the other fault zones had a steeper dip and are usually oriented perpendicular to the tunnel axis.

The fault zone known as ”Jana” is a rock layer ranging from 5-10 that is significantly more fractured and fragmented than the surrounding rock, extending for approximately 100 metres along the tunnel.
 

HOW TBM OLGA GOT ITS NAME

The naming competition was organised in collaboration with RegionalMedien Austria AG.
As with her “twin sister”, TBM Wilma, the brief was to find a female first name. The initial letter had to reflect the respective main tunnel: “O” for the eastern main tunnel and “W” for the western main tunnel (‘O’ stands for Ost, the German word for ‘east’).

From the many entries submitted, the winning suggestion came from Ms Elisabeth Wolf from Axams, a reader of MeinBezirk. She proposed the name Olga for the TBM that would excavate the BBT’s eastern main tunnel – a truly fitting name.

Olga means “the blessed one”. A fitting name, as this blessing accompanied the miners in their daily work underground – even on an extraordinary construction project such as the Brenner Base Tunnel.