The contract for largest construction lot in Austria has been awarded

- The Pfons-Brenner construction lot includes 50 kilometres of tunnel

- The bidding consortium led by PORR made the best offer and were awarded the contract, for about a billion Euro

The award of the largest construction lot for the Brenner Base Tunnel in Austria, Pfons-Brenner, was a further important step in building the longest underground railway connection today.

The Brenner Base Tunnel company, BBT SE, awarded the contract on March 23rd 2018 to the bidder consortium consisting of PORR Bau GmbH, G. Hinteregger & Söhne Baugesellschaft m.b.H., Società Italiana per Condotte d’Acqua S.p.A. and Itinera S.p.A.

This consortium will build the largest stretch of the BBT project in Austria. The contract is worth EUR 966,058,438.46. The award came after several bidders had presented appeals to the Austrian administrative court, which were however rejected and the consortium headed by PORR was confirmed as awardee.

BBT  - a railway project for future generations
The Austrian CEO of BBT SE, Prof. Konrad Bergmeister, calls the award of this huge contract a further important milestone in the project: „This award has launched the main construction phase of the European project of the century. Over 80% of the construction work for the Brenner Base Tunnel has now been awarded. The construction of the tunnel is a requirement for European transport policy and for the development of European rail corridors that will be an advantage especially for future generations.”

Pfons-Brenner construction lot
The stretch includes the construction of 37 km of main tubes between Pfons and the Brenner pass, about nine km of exploratory tunnel and the emergency stop in St. Jodok. The two main tubes will be built using tunnel boring machines. The other stretches will be built by blasting. Construction is expected to last six years.
This construction lot will produce about four million cubic metres of spoil. About a third of the spoil in the Pfons-Brenner stretch can be recycled as additives to produce concrete, tubbing rings or filter gravel. The spoil that cannot be recycled will be carried by automatic conveyor belts directly to the largest disposal site for the BBT in the Padaster valley. There will be no spoil transports through residential areas. 

The transports of material will either take place via rail and a specially built rail line from the station in Steinach or via the Brenner highway through the Saxen tunnel at the construction site itself.

The Brenner Base Tunnel - the longest underground railway connection in the world
The works for the 64-kilometre Brenner Base Tunnel are ongoing at several construction sites at the same time both in Austria and in Italy. In mid- March 2018 over 80 kilometres, meaning a good third of the 230 km of tunnel to be excavated had already been completed, including 23 km of main tunnels, 29 km of exploratory tunnel and about 28 km of access, rescue and logistic tunnels. Currently, there are four tunnel construction lots under way besides the restructuring and expansion works on the stations in Innsbruck and Fortezza. In Alto Adige, work is ongoing 24/7 at the Isarco river underpass construction site north of Fortezza, on the Mules 2-3 construction site (from Mules to Brenner) and, in Tyrol, at Wolf/Steinach for the Pfons-Brenner construction site and in Ahrental for the Tulfes-Pfons construction site.

Basic information:

  • Length of the BBT (including the Innsbruck bypass) Tulfes Portal to Fortezza Portal: 64 km
  • Length of the BBT (Innsbruck Portal to Fortezza Portal): 55 km
  • Maximum Overburden: 1.800 m
  • Inner diameter of the main tunnels: 8 m
  • Slope: 4,0 ‰ – 6,7 ‰
  • Design speed for freight traffic: 120 km/h
  • Design speed for passenger traffic: 250 km/h
  • Emergency stops: Innsbruck, St. Jodok, Trens
  • Spoil: 17 million m³
  • Excavation methods: 30 % Drill and Blasting, 70 % Tunnel boring machine