PROJECT PROGRESS

Currently, around 95% of the about 230 kilometre long tunnel system has been excavated.

In order to construct the complex tunnel system efficiently, the BBT project has been divided into several construction sections, so-called construction lots. This makes it possible to proceed with multiple excavation methods simultaneously in different locations along the new line.

OVERALL PROJECT PROGRESS

220 km
Tunnel Icon
230 km

Of the total of approximately 230 kilometres of tunnel to be built, 220 kilometres have been excavated for the BBT tunnel system to date.

KILOMETRES
114

OF RAILWAY TUNNEL

KILOMETRES
57

OF EXPLORATION TUNNEL or SERVICE TUNNEL

KILOMETRES
49

ACCESS TUNNEL, RESCUE TUNNEL AND LOGISTICS TUNNEL

KILOMETRES
220

OF WHICH HAVE BEEN EXCAVATED TO DATE

There are currently three active construction lots, one of which is located in Italy and two in Austria.