BBT SE  » Project » Basic data

Construction progress

Aica-Mules

Basic data

TEN 1 axis: Berlin–Palermo, Milan–Bologna 2,400 km
TEN 1 axis in operation or under construction 65 %
Length of the new Brenner railway line from Munich to Verona 425 km
Total tunnel length from the Innsbruck bypass to Fortezza 64 km
Length of the base tunnel from the Innsbruck portal to the Fortezza portal 55 km
Internal diameter of main tunnels 8.1 m
Internal diameter of exploratory tunnel min. 5 m
Longitudinal grade 4.0 ‰6.7 ‰
Operating speed for goods trains max. 160 km/h
Operating speed for passenger trains max. 250 km/h
Energy supply for railway traction 25 kV 50 Hz
Control and command system ETCS Level 2
Elevation at the upper surface of the rails at the Innsbruck portal 608.80 m
Elevation at the upper surface of the rails at the highest point 794 m
   
Elevation at the upper surface of the rails at the Fortezza portal 747.20 m
Expected costs (price basis: 01.01.2010) 7,460 Mio. €
Expected costs including risks that are presumed to occur but are not quantifiable (price basis: 01.01.2010) 8,062 Mio. €
Planning and construction phases:
Phase I: preliminary project and prospection
Phase II: final project and Environmental Impact Assessment
Phase IIa: exploratory section
Phase III: main tunn

1999–2003

20032010
20072013
2011–2025