Alternative hiking trail opens in the Sill Gorge

The new trail which was set up makes the recreational area accessible despite the construction works

Isarco River Underpass construction site: ground freezing for the first main tube has begun

After the successful excavation works for the first connecting tunnel below the Isarco river, the next freezing phase...

Isarco Underpass construction site: completed shift of the existing railway line

On February 7th, 2021 the tracks of the existing Brenner railway line have been shifted.

H41 construction lot “Sill Gorge - Pfons” to be tendered

On January, 29th 2021, the Sill Gorge-Pfons construction lot (H41) was tendered at a European level with a contract...

Isarco River Underpass construction site: the first track of the existing railway line has been shifted

On January 10th, 2021 the first northbound track of the existing Brenner railway line has been shifted.

Isarco underpass construction site: first breakthrough under the Isarco river

The first breakthrough through the frozen soil under the Isarco river took place on Friday, November 6th at 3:30 p.m.